Tennessee Contractor Business and Law Examination Exam Prep
Free practice questions

Free TN-BL Practice Questions

10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The TN-BL exam has 50 questions and runs 2 hours 30 minutes.

These 10 free TN-BL questions are organized by exam domain, so you can see how each part of the Tennessee Contractor Business and Law Examination blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Business Organization

Question 1

A controller discovers that one accounts-payable clerk can create vendors, approve invoices, release electronic payments, and reconcile the bank account. Which change best reduces the opportunity for vendor-payment fraud without disrupting legitimate purchasing?

Show answer & explanation

Correct answer: B - Separate vendor setup, payment authorization, and bank reconciliation among different people

Question 2

An owner tells a supplier that the project superintendent may place routine material orders. The owner later revokes that authority privately but does not notify the supplier. The superintendent then places another routine order, and the supplier relies on the owner's earlier representation. Which doctrine most strongly supports binding the company to the order?

Show answer & explanation

Correct answer: D - Apparent authority

Domain 2: Licensing

Question 3

A Tennessee owner plans one renovation with a total labor-and-material cost of $27,600. To avoid licensing requirements, the owner proposes issuing the same contractor three separate $9,200 purchase orders for the project. What is the proper licensing conclusion?

Show answer & explanation

Correct answer: A - Treat the work as one $27,600 project; the contractor-license threshold is met

Question 4

A contractor's current assets are $310,000, current liabilities are $190,000, total assets are $610,000, and total liabilities are $450,000. Assume the financial statement is accepted, the contractor is not using the BC-A/r classification, and no other restriction applies. The contractor wants to submit a $1,280,000 bid. Which statement is accurate?

Show answer & explanation

Correct answer: C - The base limit is $1,200,000, and the $1,280,000 bid is within the ordinary bid tolerance

Domain 3: Estimating and Bidding

Question 5

The lowest mechanical subcontract quote excludes controls, startup testing, freight, and the payment bond required by the bid documents. Two higher quotes include all four items. Before recommending an award, how should the estimator compare the proposals?

Show answer & explanation

Correct answer: D - Level every quote to the same scope and commercial assumptions before making the selection

Question 6

An estimate shows total project cost of $720,000. Management requires a 20% gross margin measured on the final selling price, not a 20% markup on cost. What bid price meets that requirement?

Show answer & explanation

Correct answer: A - $900,000

Question 7

On a covered public bid, the apparent low bidder has adequate experience, staffing, finances, and licensing, but omitted the required signed bid bond from its submission. How should the omission be classified?

Show answer & explanation

Correct answer: B - The bid may be nonresponsive even though the bidder appears responsible

Domain 4: Contracts

Question 8

During excavation, the owner directs the contractor to install a redesigned shoring system immediately under a contract clause permitting unilateral changes. The contractor must proceed, but the price and time adjustment have not been agreed. Which instrument fits this situation?

Show answer & explanation

Correct answer: C - Construction change directive

Question 9

On a covered Tennessee commercial project, an undisputed progress payment is past due. The contractor serves the required written stop-work notice on the proper parties today, and no additional contractual waiting period applies. What course is consistent with the Tennessee Prompt Pay Act?

Show answer & explanation

Correct answer: B - Wait through the 10-calendar-day cure period, then suspend only if the payment remains unpaid

Domain 5: Project Management

Question 10

At the status date, a project has planned value of $800,000, earned value of $720,000, and actual cost of $600,000. Which pair correctly states the cost and schedule performance indexes and their meaning?

Show answer & explanation

Correct answer: D - CPI 1.20 and SPI 0.90: under budget and behind plan

The rest of the TN-BL blueprint

The TN-BL exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more TN-BL questions with explanations.

Continue in the free practice test →

View plans